Weld County data center foes turn in 30,000 signatures; Littleton weighs moratorium


Opponents of a proposed data center in Weld County say they gathered more than 30,000 signatures in two weeks on two petitions aimed at stopping the project and reshaping how future data centers are approved.
The petition drive, announced this week by Protect Our Water and Energy Resources, targets the 41-acre Global AI data center that Weld County commissioners approved just outside Windsor. One petition would send that approval to a public vote. The second, a citizen initiative, would require any future data center development or expansion to win approval in a countywide election before proceeding, in addition to existing county and state standards.
Organizers said each petition has about 15,000 signatures. The county must verify at least 9,120 valid signatures, equal to 5% of voters who cast ballots in the 2024 general election, before either measure can move forward.
If the signatures are confirmed, the citizen initiative would qualify for a special election. The referendum would first go to the Weld County Board of County Commissioners, who could either reverse Global AI’s approval or send the question to voters alongside the initiative.
Weld County Clerk Carly Koppes said the county has not held a special election in decades. Based on general election costs, she said a special election could cost between $650,000 and $750,000.
The signature campaign follows months of local opposition. At two county public hearings on Global AI’s plan, nearly 60 people spoke against the project while three supported it, with residents raising concerns about transparency, energy use and environmental effects. Commissioners nevertheless voted unanimously on Sept. 9 to approve the project’s Use by Special Review application.
The petition deadline tied to the general election had been July 6, roughly two months before commissioners approved Global AI’s permit.
Windsor resident Kurt Gulder, who has lived in Weld County for 11 years, said he and his wife, Jeanette, went to a King Soopers parking lot in Windsor to sign both petitions after hearing about the effort on social media. The couple live just over a mile from the Global AI site and are worried about the project’s environmental impacts.
“All they see is the big shiny tax dollars that are supposedly going to be coming in from this project,” Gulder said of the commissioners. “We couldn’t wait to go out and sign up.”
POWER is an issue committee backed by Broe Real Estate. Broe owns the Great Western Industrial Park, which neighbors the site that Global AI is developing.
The dispute in Weld County is unfolding as other Colorado communities move to slow data center development. Littleton is now weighing a moratorium on data centers, joining a growing list of cities that have pressed pause while officials consider new rules.
Littleton’s proposal would temporarily stop new data center projects while the city studies land use, infrastructure and policy questions tied to the facilities.
The next step in Weld County is signature verification. If county officials confirm enough valid signatures, commissioners will decide whether to repeal Global AI’s approval or place both questions before voters in a special election.